How SAAQclic Became a $1.1 Billion Failure

A visual breakdown of the procurement process that led to Quebec's costliest IT scandal

In 2017, Quebec's Ministry of Health signed a contract with SAP for a new health information system. The initial budget was $458 million. By 2023, the final cost exceeded $1.1 billion—a 140% increase. This flowchart maps the critical decision points where competitive oversight was bypassed.

Flowchart 1: The Procurement Decision Path

Where Did the Procurement Process Fail?

2017: Ministry of Health (MSSS)
Needs new IT system for health data
Will there be competitive bidding?
REGULATORY REQUIREMENT
Public call for tenders Required by Quebec procurement law
Multiple suppliers submit bids
Independent evaluation committee Scores based on criteria
Best value contract awarded
Competitive market pricing
WHAT ACTUALLY HAPPENED
Direct negotiation with SAP only No public tender
Sole-source exemption claimed Justification: "System integration critical"
No competitive bids received No price comparison possible
SAP contract signed: $458M October 2017
No cost controls
Final bill: $1.1 billion (+140%)

Flowchart 2: Timeline of Failures

October 2017
Contract signed with SAP ($458M)
2018-2019
Early cost escalation begins Project scope expands
2020
Budget revision: $650M +42% increase, limited public disclosure
2021
Internal auditors flag cost overruns Warnings not acted upon by senior officials
2022
Project delays mount Revised budget: $890M
2023
System finally delivered Final cost: $1.1 billion
2024-2025
Public outcry, investigation launched
2026: Auditor General Report
586 pages documenting failures 75 days of hearings, 120+ witnesses

Flowchart 3: Oversight and Accountability

Who Should Have Intervened?

Cost overruns detected (2020-2021)
Who had oversight authority?
Internal
Internal Auditors
Did they act?
YES
Raised concerns in 2021 But warnings ignored by management
Ministry
MSSS Senior Officials
Did they act?
NO
Did not halt the contract Continued payments despite escalation
Legislative
Treasury Board
Were they informed?
UNCLEAR
Limited documentation Evidence suggests partial disclosure
Result: Accountability Failure
No intervention until project completion

Flowchart 4: Simple Cause and Effect

Single-source contract (no competition)
Enabled by
No market pressure on pricing
Combined with
Inadequate internal oversight
Led to
Unchecked cost escalation
Resulted in
$642 Million Cost Overrun
$458M → $1.1B (+140%)